Construction Dispute Law in Arizona

When a property owner and a general contractor contract for a construction project to take place on some property in Cottonwood, Arizona, whether it's a house, some landscaping, or a remodeling project, there is always a chance that something can go wrong. In fact, at least a very minor setback may be more likely than not.

Most often, landowners and construction contractors are able to resolve minor to moderate disagreements between themselves, and litigation is rarely necessary. Nobody likes litigation, so, to this end, most construction contracts have built-in remedies in case something goes wrong, like set price reductions if construction is delayed.

And even if disputes can't be resolved so easily, the courts still don't necessarily have to get involved. For example, a construction contract may require mediation before any further action is taken. Mediation is a process by which a third party tries to guide the parties to the dispute to a settlement. The mediator cannot, however, render any binding decision. Another avenue is arbitration. This is where the parties go to a private arbitration service, which can render a binding judgment (generally enforceable through contract law, as the parties agree in advance to abide by the arbitrator's decision). Arbitration has benefits over litigation, as the parties can have a say in choosing the arbitrator (allowing them to have their case arbitrated by an expert on construction disputes, for example).

Litigation of construction disputes in Cottonwood, Arizona can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) occasions where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Cottonwood, Arizona

Delays: Some minor delays in a construction project are all but guaranteed to occur. Usually, if contracts require a specific completion date, the contractor will give itself longer than the project would take under ideal circumstances, to account for possible delays. Furthermore, construction contracts usually attempt to insure against delays, such as imposing fees on contractors if the project is delayed beyond a certain point. If no such clause is included in a contract, a court will usually award the client damages that could have been reasonably anticipated at the time the contract was entered into.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will usually argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be liable for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractors: Subcontractors are hired by general contractors to assist them in large construction projects, usually specialized tasks like installing plumbing. Nonetheless, no matter how much of the work is performed by subcontractors, the general contractor (the one that the client actually hired to do the project) is liable to the landowner as if it were doing all the work itself. This essentially means that, if a subcontractor messes up, the general contractor is the one who gets sued. But all is not lost in such a situation. If the general contractor has to compensate the owner because of the mistakes of a subcontractor, it can sue the subcontractor for whatever it had to pay to the landowner.

Mechanic's Lien: When a contractor wins a case against a client for nonpayment of the contract price, and the client still declines to pay, there is a problem: a monetary judgment means next to nothing if it can't be enforced. To solve this problem, the mechanic's lien has been developed. Essentially, if a landowner refuses to pay a contractor, even in the face of a court order, the court can force a sale of the property that the contractor worked on, along with all the improvements on it, and then give the funds to the contractor, to secure payment.

Can a Cottonwood, Arizona Attorney Help?

Construction disputes can be time-consuming and costly. Hiring a reputable Cottonwood, Arizona real estate attorney can make it much easier to deal with such disputes, and help you avoid litigation, or prevail if litigation becomes necessary.