Construction Dispute Law in Wisconsin

Construction contractors and landowners in Tomah, Wisconsin sometimes end up in disagreements when a project that the landowner contracted for doesn't go exactly to plan. Truth be told, in any significant construction project, a few minor disputes are almost guaranteed.

Most often, landowners and construction contractors are able to resolve minor to moderate disagreements between themselves, and litigation is rarely necessary. Nobody likes litigation, so, to this end, most construction contracts have built-in remedies in case something goes wrong, like set price reductions if construction is delayed.

Even if a third party gets incorporated, it does not always need to be a court. Private mediators can assist the parties reach a settlement, or a private arbitrator who is an expert on construction litigation can render a binding decision, if mediation and negotiation fail and the parties can't resolve their dispute.

Litigation of construction disputes in Tomah, Wisconsin can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) occurrences where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Tomah, Wisconsin

Delays in Construction: Delays are frequently points of contention between contractors and landowners. Contracts sometimes have clauses which explicitly state that the project needs to be completed by a certain date, or penalties will be imposed on the contractor (reduced payments, for example). However, if the contract doesn't contain such built-in remedies, or one party refuses to abide by them, litigation may be necessary. If a contractor causes a delay that it could have prevented, it will typically be liable to the landowner for any harm resulting from it.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will typically argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be responsible for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractor Disputes: With very considerable construction projects, general contractors don't always have the resources to do all the work themselves, so they hire other contractors to do some of the work for them. Nonetheless, it is the general contractor who is ultimately responsible to the owner for the satisfactory completion of the project. So, it is very critical to the general contractor that subcontractors do a good job. If the subcontractor causes a delay or other issue, and the owner sues the general contractor as a result, the general contractor can then go after the subcontractor to recover whatever it lost in the lawsuit.

Mechanic's Liens: A mechanic's lien is a way for a contractor to secure payment if a landowner declines to pay. In such cases, if the contractor sues and wins, he or she can sometimes impose a mechanic's lien on the property he or she just worked on. This permits the contractor to force a sale of the property to cover the judgment. It is usually used when other attempts to secure payment fail.

Can a Tomah, Wisconsin Attorney Help?

If you are involved in a dispute over a construction project, you should try to avoid litigation, and settle the matter as amicably as possible. However, litigation is sometimes imperative, and a Tomah, Wisconsin construction disputes attorney can be of great help.