Construction Dispute Law in Washington

Construction contractors and landowners in Sedro Woolley, Washington sometimes end up in disputes when a project that the landowner contracted for doesn't go exactly to plan. Truth be told, in any significant construction project, a few minor disputes are almost guaranteed.

Typically, contractors and landowners can resolve minor disputes amongst themselves, without having to resort to litigation. Frequently, construction contracts contain built-in remedies for mistakes and delays that can be easily corrected, such as payments to the owner for every day the project is delayed.

Even if someone else needs to get engaged to resolve a dispute, this does not automatically mean litigation is necessary. For example, the parties might attempt mediation, in which a neutral third party tries to help guide the parties to an agreement, but cannot render a binding decision himself. They might also agree to arbitration, during which a third party is able to render a binding decision. Arbitration is typically done through a private company, and may cost less than litigation, and is overseen by an arbitrator who is an expert in the relevant field.

Litigation of a Sedro Woolley, Washington construction dispute is never something that anyone wants to do. Nonetheless, there are sometimes no other options.

Examples of Construction Disputes That Might Lead to Litigation in Sedro Woolley, Washington

Major Delays: If the contractor or a subcontractor is at fault in causing a considerable delay to a project (several months, for example), this may lead to a lawsuit. If the contract stated that time was of the essence for some reason (maybe the project was a new store that the owner hoped to open before the holiday shopping season, for example), a court can typically award the owner any damages that were caused by the delay.

Refusal to Pay: Contractors can be on the other side of legal disputes, as well. Sometimes, the landowners who hired them refuse to pay. This is typically because the landowner believes that the contractor didn't perform under the terms of the contract, or that the work was unsatisfactory. If this is the case, it may ultimately be up to a court to decide who is right. If the contractor did, in fact, do poor work, the landowner will be excused, at least in part, from his duty to pay. If, on the other hand, the work was satisfactory, the court will order the landowner to pay the contract price immediately, and may award additional damages if the refusal to pay was done in bad faith, or if it caused foreseeable economic harm to the contractor.

Subcontractors: With big construction projects, contractors typically hire other, smaller contractors to do some of the work for them. This is typically work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. However, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Liens: If the contractor sues a land owner and wins, he will likely obtain a monetary judgment. If the owner refuses to pay, the contractor needs some way to recover. This is where the mechanic's lien comes into play. It permits a contractor to force the sale of the land or other real property that he just worked on, and use those proceeds to cover costs.

Can a Sedro Woolley, Washington Attorney Help?

Disputes over construction delays or defects can be extremely taxing. Therefore, getting an efficient Sedro Woolley, Washington real estate attorney might mean the difference between success or failure in your business ventures.