Construction Dispute Law in South Carolina

Landowners and contractors in Cheraw, South Carolina commonly contract with each other for major construction projects. With any large construction projects, some small delays or problems are all but inevitable, but they don't usually derail the project or lead to major disputes between the parties.

Most often, landowners and construction contractors are able to resolve minor to moderate disputes between themselves, and litigation is rarely necessary. Nobody likes litigation, so, to this end, most construction contracts have built-in remedies in case something goes wrong, like set price reductions if construction is delayed.

Even if someone else needs to get immersed to resolve a dispute, this does not automatically mean litigation is necessary. For example, the parties might attempt mediation, in which a neutral third party tries to help guide the parties to an agreement, but cannot render a binding decision himself. They might also agree to arbitration, during which a third party is able to render a binding decision. Arbitration is normally done through a private company, and may cost less than litigation, and is overseen by an arbitrator who is an expert in the relevant field.

Litigation of a Cheraw, South Carolina construction dispute is never something that anyone wants to do. Nonetheless, there are sometimes no other options.

Examples of Construction Disputes That Might Lead to Litigation in Cheraw, South Carolina

Delays: If the contractor is culpable in a major delay in a construction project (a delay of weeks or months, for example), a lawsuit could result. If the contract specifically states that completion by a particular date is very important, or the builder has a good reason to know this, a court will often award the owner compensation for any economic harm caused by a delay.

Refusal to Pay: Contractors can be on the other side of legal disputes, as well. Sometimes, the landowners who hired them refuse to pay. This is normally because the landowner believes that the contractor didn't perform under the terms of the contract, or that the work was unsatisfactory. If this is the case, it may ultimately be up to a court to decide who is right. If the contractor did, in fact, do poor work, the landowner will be excused, at least in part, from his duty to pay. If, on the other hand, the work was satisfactory, the court will order the landowner to pay the contract price immediately, and may award additional damages if the refusal to pay was done in bad faith, or if it caused foreseeable economic harm to the contractor.

Subcontractor Disputes: When a construction company is contracted to complete a large project, there is normally a great deal of specialized work to be done which they aren't equipped to handle. As a result, they hire other contractors, who, in this arrangement, are subcontractors, to do some of the work. However, the general contractor (the one that the landowner hired to do the work) is still responsible for the completion of the project - if a subcontractor causes a problem, the general contractor is on the hook for it. This sometimes leads to landowners suing general contractors for the mistakes of subcontractors. If the general contractor loses, and has to pay the client, the general contractor can then sue the subcontractor for whatever amount of money it had to pay.

Mechanic's Liens: If the contractor sues a land owner and wins, he will likely obtain a monetary judgment. If the owner refuses to pay, the contractor needs some way to recover. This is where the mechanic's lien comes into play. It authorizes a contractor to force the sale of the land or other real property that he just worked on, and use those proceeds to cover costs.

Can a Cheraw, South Carolina Attorney Help?

If you have a construction dispute, you should first try to resolve it amicably with the other party. If this fails, it is almost always necessary to hire a Cheraw, South Carolina construction disputes attorney, who can advise you on the next steps in the process.