Construction Dispute Law in Oklahoma

Owners of real estate in Guymon, Oklahoma frequently contract with other parties ("contractors") for construction on the property they own. Such projects are likely to suffer at least a few minor setbacks, and any project also carries the risk of major setbacks, delays, or unexpected costs.

In the overwhelming majority of cases, however, these problems are resolvable, and do not lead to major disputes. Being rational, business-minded adults, landowners and construction contractors are typically able to resolve disputes amongst themselves. After all, both stand to gain if the project is completed, and the contractor is paid.

And even if disputes can't be resolved so easily, the courts still don't necessarily have to get engaged. For example, a construction contract may require mediation before any further action is taken. Mediation is a process by which a third party tries to guide the parties to the dispute to a settlement. The mediator cannot, however, render any binding decision. Another avenue is arbitration. This is where the parties go to a private arbitration service, which can render a binding judgment (usually enforceable through contract law, as the parties agree in advance to abide by the arbitrator's decision). Arbitration has benefits over litigation, as the parties can have a say in choosing the arbitrator (allowing them to have their case arbitrated by an expert on construction disputes, for example).

Litigation of construction disputes in Guymon, Oklahoma can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) occurrences where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Guymon, Oklahoma

Delays: Some minor delays in a construction project are all but guaranteed to occur. Typically, if contracts require a specific completion date, the contractor will give itself longer than the project would take under ideal circumstances, to account for possible delays. Moreover, construction contracts usually attempt to insure against delays, such as imposing fees on contractors if the project is delayed beyond a certain point. If no such clause is included in a contract, a court will usually award the client damages that could have been reasonably anticipated at the time the contract was entered into.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will typically argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be responsible for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractor Disputes: With very considerable construction projects, general contractors don't always have the resources to do all the work themselves, so they hire other contractors to do some of the work for them. Nonetheless, it is the general contractor who is ultimately responsible to the owner for the satisfactory completion of the project. So, it is very important to the general contractor that subcontractors do a good job. If the subcontractor causes a delay or other issue, and the owner sues the general contractor as a result, the general contractor can then go after the subcontractor to recover whatever it lost in the lawsuit.

Mechanic's Liens: Sometimes, when a contractor wins in a case against the landowner who hired him or her, and obtains a court order for payment, the contractor will still refuse to pay. Since a money judgment isn't worth much without a way to enforce it, the laws of many states have evolved to permit what's known as a "mechanic's lien." As a last resort, if a landowner refuses to pay the contractor for work done on the property, the contractor can force a sale of the property, and keep the proceeds, up to the amount of money owed.

Can a Guymon, Oklahoma Attorney Help?

Construction disputes can be time-consuming and costly. Hiring a reliable Guymon, Oklahoma real estate attorney can make it much easier to deal with such disputes, and help you avoid litigation, or prevail if litigation becomes necessary.