Construction Dispute Law in New York

Owners of real estate in Coram, New York commonly contract with other parties ("contractors") for construction on the property they own. Such projects are likely to suffer at least a few minor setbacks, and any project also carries the risk of major setbacks, delays, or unexpected costs.

In the majority of cases, it's possible for landowners and contractors to resolve disagreements amicably. There are many ways to do this, such as a simple verbal agreement to lower the contract price due to a mistake made by the contractor, for example, or an agreement to a slight price increase in the event of unforeseen obstacles beyond the control of either party.

Even if the parties can't easily resolve their disputes, and someone else needs to intervene, that somebody doesn't always need to be a judge or jury. Many construction disagreements call for mediation, during which a neutral third party helps the parties to the dispute negotiate a settlement. They might also go through arbitration, during which a third party renders a binding decision.

Litigation of construction disputes in Coram, New York can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) times where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Coram, New York

Major Delays: If the contractor or a subcontractor is at fault in causing a massive delay to a project (several months, for example), this may lead to a lawsuit. If the contract stated that time was of the essence for some reason (maybe the project was a new store that the owner hoped to open before the holiday shopping season, for example), a court can normally award the owner any damages that were caused by the delay.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will normally argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be accountable for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractors: With big construction projects, contractors normally hire other, smaller contractors to do some of the work for them. This is normally work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. Nonetheless, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Lien: When a contractor wins a case against a client for nonpayment of the contract price, and the client still declines to pay, there is a problem: a monetary judgment means next to nothing if it can't be enforced. To solve this problem, the mechanic's lien has been developed. Basically, if a landowner refuses to pay a contractor, even in the face of a court order, the court can force a sale of the property that the contractor worked on, along with all the improvements on it, and then give the funds to the contractor, to secure payment.

Can a Coram, New York Attorney Help?

If you are involved in a dispute over a construction project, you should try to avoid litigation, and settle the matter as amicably as possible. However, litigation is sometimes crucial, and a Coram, New York construction disputes attorney can be of great help.