Construction Dispute Law in Mississippi

Owners of real estate in Amory, Mississippi frequently contract with other parties ("contractors") for construction on the property they own. Such projects are likely to suffer at least a few minor setbacks, and any project also carries the risk of major setbacks, delays, or unexpected costs.

Typically, contractors and landowners can resolve minor disputes amongst themselves, without having to resort to litigation. Frequently, construction contracts contain built-in remedies for mistakes and delays that can be easily corrected, such as payments to the owner for every day the project is delayed.

Even if the parties can't easily resolve their disputes, and someone else needs to intervene, that somebody doesn't always need to be a judge or jury. Many construction disputes call for mediation, during which a neutral third party helps the parties to the dispute negotiate a settlement. They might also go through arbitration, during which a third party renders a binding decision.

Litigating a construction dispute in Amory, Mississippi is definitely not something that anybody likes doing. However, it is sometimes necessary, as a last resort.

Examples of Construction Disputes That Might Lead to Litigation in Amory, Mississippi

Major Delays: If the contractor or a subcontractor is at fault in causing a considerable delay to a project (several months, for example), this may lead to a lawsuit. If the contract stated that time was of the essence for some reason (maybe the project was a new store that the owner hoped to open before the holiday shopping season, for example), a court can typically award the owner any damages that were caused by the delay.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will typically argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be responsible for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractors: Subcontractors are hired by general contractors to assist them in large construction projects, typically specialized tasks like installing plumbing. However, no matter how much of the work is performed by subcontractors, the general contractor (the one that the client actually hired to do the project) is liable to the landowner as if it were doing all the work itself. This basically means that, if a subcontractor messes up, the general contractor is the one who gets sued. But all is not lost in such a situation. If the general contractor has to compensate the owner because of the mistakes of a subcontractor, it can sue the subcontractor for whatever it had to pay to the landowner.

Mechanic's Lien: When a contractor wins a lawsuit against a client for nonpayment of the contract price, and the client still refuses to pay, there is a problem: a monetary judgment means next to nothing if it can't be enforced. To solve this problem, the mechanic's lien has been developed. Typically, if a landowner refuses to pay a contractor, even in the face of a court order, the court can force a sale of the property that the contractor worked on, along with all the improvements on it, and then give the proceeds to the contractor, to secure payment.

Can a Amory, Mississippi Attorney Help?

If you are involved in a dispute over a construction project, you should try to avoid litigation, and settle the matter as amicably as possible. However, litigation is sometimes necessary, and an Amory, Mississippi construction disputes attorney can be of great help.