Construction Dispute Law in Illinois

When a property owner and a general contractor contract for a construction project to take place on some property in Mount Carmel, Illinois, whether it's a house, some landscaping, or a remodeling project, there is always a chance that something can go wrong. In fact, at least a very minor setback may be more likely than not.

In the overwhelming majority of instances, however, these problems are resolvable, and do not lead to major disputes. Being rational, business-minded adults, landowners and construction contractors are usually able to resolve disputes amongst themselves. After all, both stand to gain if the project is completed, and the contractor is paid.

And even if disputes can't be resolved so easily, the courts still don't necessarily have to get involved. For example, a construction contract may require mediation before any further action is taken. Mediation is a process by which a third party tries to guide the parties to the dispute to a settlement. The mediator cannot, however, render any binding decision. Another option is arbitration. This is where the parties go to a private arbitration service, which can render a binding judgment (generally enforceable through contract law, as the parties agree in advance to abide by the arbitrator's decision). Arbitration has advantages over litigation, as the parties can have a say in choosing the arbitrator (allowing them to have their case arbitrated by an expert on construction disputes, for example).

Litigation of construction disputes in Mount Carmel, Illinois can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) occasions where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Mount Carmel, Illinois

Delays: If the contractor is culpable in a major delay in a construction project (a delay of weeks or months, for example), a lawsuit could result. If the contract specifically states that completion by a certain date is very important, or the builder has a good reason to know this, a court will often award the owner compensation for any economic harm caused by a delay.

Owner's Refusal to Pay: If the contractor completes the project, and the owner refuses to pay the agreed-upon price, the contractor will usually file a lawsuit to recover what is owed. Of course, the owner will usually claim that there is a good reason for not paying, arguing that the contractor didn't conform to the project's specifications, or that the quality of construction was unacceptably poor. In such a case, the court will have to determine if the contractor actually breached the contract by doing shoddy work, which could, at least in part, excuse the owner's duty to pay.

Subcontractors: With big construction projects, contractors usually hire other, smaller contractors to do some of the work for them. This is usually work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. However, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Liens: If the contractor sues a land owner and wins, he will likely obtain a monetary judgment. If the owner refuses to pay, the contractor needs some way to recover. This is where the mechanic's lien comes into play. It allows a contractor to force the sale of the land or other real property that he just worked on, and use those proceeds to cover costs.

Can a Mount Carmel, Illinois Attorney Help?

Disputes over construction delays or defects can be extremely taxing. Therefore, getting an experienced Mount Carmel, Illinois real estate attorney might mean the difference between success or failure in your business ventures.