Construction Dispute Law in Iowa

When a property owner and a general contractor contract for a construction project to take place on some property in Sheldon, Iowa, whether it's a house, some landscaping, or a remodeling project, there is always a risk that something can go wrong. In fact, at least a very minor setback may be more likely than not.

In the overwhelming majority of cases, however, these problems are resolvable, and do not lead to major disputes. Being rational, business-minded adults, landowners and construction contractors are normally able to resolve disputes amongst themselves. After all, both stand to gain if the project is completed, and the contractor is paid.

Even if the parties can't easily resolve their disputes, and someone else needs to intervene, that somebody doesn't always need to be a judge or jury. Many construction disagreements call for mediation, during which a neutral third party helps the parties to the dispute negotiate a settlement. They might also go through arbitration, during which a third party renders a binding decision.

Litigating a construction dispute in Sheldon, Iowa is definitely not something that anybody likes doing. Nonetheless, it is sometimes necessary, as a last resort.

Examples of Construction Disputes That Might Lead to Litigation in Sheldon, Iowa

Major Delays: If the contractor or a subcontractor is at fault in causing a massive delay to a project (several months, for example), this may lead to a lawsuit. If the contract stated that time was of the essence for some reason (maybe the project was a new store that the owner hoped to open before the holiday shopping season, for example), a court can normally award the owner any damages that were caused by the delay.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will normally argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be accountable for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractors: Subcontractors are hired by general contractors to assist them in large construction projects, normally specialized tasks like installing plumbing. Nonetheless, no matter how much of the work is performed by subcontractors, the general contractor (the one that the client actually hired to do the project) is liable to the landowner as if it were doing all the work itself. This essentially means that, if a subcontractor messes up, the general contractor is the one who gets sued. But all is not lost in such a situation. If the general contractor has to compensate the owner because of the mistakes of a subcontractor, it can sue the subcontractor for whatever it had to pay to the landowner.

Mechanic's Liens: A mechanic's lien is a way for a contractor to secure payment if a landowner declines to pay. In such cases, if the contractor sues and wins, he or she can sometimes impose a mechanic's lien on the property he or she just worked on. This authorizes the contractor to force a sale of the property to cover the judgment. It is usually used when other attempts to secure payment fail.

Can a Sheldon, Iowa Attorney Help?

If you have a construction dispute, you should first try to resolve it amicably with the other party. If this fails, it is almost always imperative to hire a Sheldon, Iowa construction disputes attorney, who can advise you on the next steps in the process.