Construction Dispute Law in Iowa

When a property owner and a general contractor contract for a construction project to take place on some property in Newton, Iowa, whether it's a house, some landscaping, or a remodeling project, there is always a risk that something can go wrong. In fact, at least a very minor setback may be more likely than not.

In the overwhelming majority of cases, however, these problems are resolvable, and do not lead to major disputes. Being rational, business-minded adults, landowners and construction contractors are normally able to resolve disputes amongst themselves. After all, both stand to gain if the project is completed, and the contractor is paid.

Even if the parties can't easily resolve their disputes, and someone else needs to intervene, that somebody doesn't always need to be a judge or jury. Many construction disagreements call for mediation, during which a neutral third party helps the parties to the dispute negotiate a settlement. They might also go through arbitration, during which a third party renders a binding decision.

Litigation of construction disputes in Newton, Iowa can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) times where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Newton, Iowa

Major Delays: If the contractor or a subcontractor is at fault in causing a massive delay to a project (several months, for example), this may lead to a lawsuit. If the contract stated that time was of the essence for some reason (maybe the project was a new store that the owner hoped to open before the holiday shopping season, for example), a court can normally award the owner any damages that were caused by the delay.

Refusal to Pay: Disagreements can also arise from a client's refusal or inability to hold up his end of the deal. Sometimes, once a project is complete, or nearly so, a landowner will express an unwillingness to pay the contractor for his services. There might be a variety of reasons for this - sudden loss of money, or dissatisfaction with the quality of the work are a few examples. It's rare that a client will refuse to pay a contractor simply because they don't feel like it (and if that is the reason, they'll normally come up with a better one to argue in court). In these cases, a court will occasionally have to decide if the client is obligated to pay the full price. If the work was, indeed, not up to the standards laid out in the contract, the contractor is not entitled to the full price, but is still entitled to the actual value of the work, even if it's substantially less than the contract price.

Subcontractors: Subcontractors are hired by general contractors to assist them in large construction projects, normally specialized tasks like installing plumbing. Nonetheless, no matter how much of the work is performed by subcontractors, the general contractor (the one that the client actually hired to do the project) is liable to the landowner as if it were doing all the work itself. This essentially means that, if a subcontractor messes up, the general contractor is the one who gets sued. But all is not lost in such a situation. If the general contractor has to compensate the owner because of the mistakes of a subcontractor, it can sue the subcontractor for whatever it had to pay to the landowner.

Mechanic's Lien: If the contractor wins in a case against the land owner, and the court orders the owner to pay the contractor for services rendered, the contractor needs a way to secure payment, if the owner refuses. In some cases, a mechanic's lien authorizes the contractor to force the sale of the land, and any improvements to it, in order to secure payment for the services it provided.

Can a Newton, Iowa Attorney Help?

Construction disputes and disagreements can be very hard to deal with alone. The assistance of a Newton, Iowa real estate attorney can make the process of dealing with these disputes much quicker and easier.