Construction Dispute Law in Iowa

When a property owner and a general contractor contract for a construction project to take place on some property in Mount Pleasant, Iowa, whether it's a house, some landscaping, or a remodeling project, there is always a gamble that something can go wrong. In fact, at least a very minor setback may be more likely than not.

In the overwhelming majority of cases, however, these problems are resolvable, and do not lead to major disputes. Being rational, business-minded adults, landowners and construction contractors are typically able to resolve disputes amongst themselves. After all, both stand to gain if the project is completed, and the contractor is paid.

Even if the parties can't easily resolve their disputes, and someone else needs to intervene, that somebody doesn't always need to be a judge or jury. Many construction disagreements call for mediation, during which a neutral third party helps the parties to the dispute negotiate a settlement. They might also go through arbitration, during which a third party renders a binding decision.

Litigation of construction disputes in Mount Pleasant, Iowa can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) occurrences where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Mount Pleasant, Iowa

Major Delays: If the contractor or a subcontractor is at fault in causing a considerable delay to a project (several months, for example), this may lead to a lawsuit. If the contract stated that time was of the essence for some reason (maybe the project was a new store that the owner hoped to open before the holiday shopping season, for example), a court can typically award the owner any damages that were caused by the delay.

Refusal to Pay: Contractors can be on the other side of legal disagreements, as well. Sometimes, the landowners who hired them refuse to pay. This is typically because the landowner believes that the contractor didn't perform under the terms of the contract, or that the work was unsatisfactory. If this is the case, it may ultimately be up to a court to decide who is right. If the contractor did, in fact, do poor work, the landowner will be excused, at least in part, from his duty to pay. If, on the other hand, the work was satisfactory, the court will order the landowner to pay the contract price immediately, and may award further damages if the refusal to pay was done in bad faith, or if it caused foreseeable economic harm to the contractor.

Subcontractors: With big construction projects, contractors typically hire other, smaller contractors to do some of the work for them. This is typically work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. Nonetheless, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Lien: When a contractor wins a case against a client for nonpayment of the contract price, and the client still declines to pay, there is a problem: a monetary judgment means next to nothing if it can't be enforced. To solve this problem, the mechanic's lien has been developed. Typically, if a landowner refuses to pay a contractor, even in the face of a court order, the court can force a sale of the property that the contractor worked on, along with all the improvements on it, and then give the funds to the contractor, to secure payment.

Can a Mount Pleasant, Iowa Attorney Help?

If you have a construction dispute, you should first try to resolve it amicably with the other party. If this fails, it is almost always crucial to hire a Mount Pleasant, Iowa construction disputes attorney, who can advise you on the next steps in the process.