Construction Dispute Law in Colorado

When a property owner and a general contractor contract for a construction project to take place on some property in Avon, Colorado, whether it's a house, some landscaping, or a remodeling project, there is always a risk that something can go wrong. In fact, at least a very minor setback may be more likely than not.

Most often, the owners of land and contractors can end disputes before they get too serious, thus eliminating the need for litigation. Most contracts governing construction projects have built-in remedies for the most common problems, normally requiring the party that causes a delay or other problem to pay the other party a set fee.

And even if disputes can't be resolved so easily, the courts still don't necessarily have to get immersed. For example, a construction contract may require mediation before any further action is taken. Mediation is a process by which a third party tries to guide the parties to the dispute to a settlement. The mediator cannot, however, render any binding decision. Another option is arbitration. This is where the parties go to a private arbitration service, which can render a binding judgment (typically enforceable through contract law, as the parties agree in advance to abide by the arbitrator's decision). Arbitration has advantages over litigation, as the parties can have a say in choosing the arbitrator (allowing them to have their case arbitrated by an expert on construction disputes, for example).

Because of the large cost in time and money involved, litigation in Avon, Colorado is considered a last resort. However, in rare cases, it does become necessary.

Examples of Construction Disputes That Might Lead to Litigation in Avon, Colorado

Delays: Some minor delays in a construction project are all but guaranteed to occur. Normally, if contracts require a specific completion date, the contractor will give itself longer than the project would take under ideal circumstances, to account for possible delays. Additionally, construction contracts usually attempt to insure against delays, such as imposing fees on contractors if the project is delayed beyond a certain point. If no such clause is included in a contract, a court will usually award the client damages that could have been reasonably anticipated at the time the contract was entered into.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will normally argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be accountable for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractors: With big construction projects, contractors normally hire other, smaller contractors to do some of the work for them. This is normally work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. However, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Liens: Sometimes, when a contractor wins in a lawsuit against the landowner who hired him or her, and obtains a court order for payment, the contractor will still refuse to pay. Since a money judgment isn't worth much without a way to enforce it, the laws of many states have evolved to authorize what's known as a "mechanic's lien." As a last resort, if a landowner refuses to pay the contractor for work done on the property, the contractor can force a sale of the property, and keep the proceeds, up to the amount of money owed.

Can a Avon, Colorado Attorney Help?

If you are involved in a dispute over a construction project, you should try to avoid litigation, and settle the matter as amicably as possible. However, litigation is sometimes necessary, and an Avon, Colorado construction disputes attorney can be of great help.