Construction Dispute Law in Wisconsin

Construction contractors and landowners in Shawano, Wisconsin sometimes end up in disagreements when a project that the landowner contracted for doesn't go exactly to plan. Truth be told, in any significant construction project, a few minor disputes are almost guaranteed.

Most often, landowners and construction contractors are able to resolve minor to moderate disagreements between themselves, and litigation is rarely necessary. Nobody likes litigation, so, to this end, most construction contracts have built-in remedies in case something goes wrong, like set price reductions if construction is delayed.

Even if a third party gets incorporated, it does not always need to be a court. Private mediators can assist the parties reach a settlement, or a private arbitrator who is an expert on construction litigation can render a binding decision, if mediation and negotiation fail and the parties can't resolve their dispute.

Litigation of construction disputes in Shawano, Wisconsin can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) occurrences where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Shawano, Wisconsin

Delays: If the contractor is culpable in a major delay in a construction project (a delay of weeks or months, for example), a lawsuit could result. If the contract particularly states that completion by a specific date is very important, or the builder has a good reason to know this, a court will often award the owner compensation for any economic harm caused by a delay.

Refusal to Pay: Contractors can be on the other side of legal disagreements, as well. Sometimes, the landowners who hired them refuse to pay. This is typically because the landowner believes that the contractor didn't perform under the terms of the contract, or that the work was unsatisfactory. If this is the case, it may ultimately be up to a court to decide who is right. If the contractor did, in fact, do poor work, the landowner will be excused, at least in part, from his duty to pay. If, on the other hand, the work was satisfactory, the court will order the landowner to pay the contract price immediately, and may award further damages if the refusal to pay was done in bad faith, or if it caused foreseeable economic harm to the contractor.

Subcontractor Disputes: With very considerable construction projects, general contractors don't always have the resources to do all the work themselves, so they hire other contractors to do some of the work for them. Nonetheless, it is the general contractor who is ultimately responsible to the owner for the satisfactory completion of the project. So, it is very critical to the general contractor that subcontractors do a good job. If the subcontractor causes a delay or other issue, and the owner sues the general contractor as a result, the general contractor can then go after the subcontractor to recover whatever it lost in the lawsuit.

Mechanic's Lien: When a contractor wins a case against a client for nonpayment of the contract price, and the client still declines to pay, there is a problem: a monetary judgment means next to nothing if it can't be enforced. To solve this problem, the mechanic's lien has been developed. Typically, if a landowner refuses to pay a contractor, even in the face of a court order, the court can force a sale of the property that the contractor worked on, along with all the improvements on it, and then give the funds to the contractor, to secure payment.

Can a Shawano, Wisconsin Attorney Help?

Disputes over construction delays or defects can be extremely taxing. Therefore, getting an efficient Shawano, Wisconsin real estate attorney might mean the difference between success or failure in your business ventures.