Construction Dispute Law in Ohio

Owners of real estate in Marysville, Ohio often contract with other parties ("contractors") for construction on the property they own. Such projects are likely to suffer at least a few minor setbacks, and any project also carries the risk of major setbacks, delays, or unexpected costs.

In the overwhelming majority of cases, however, these problems are resolvable, and do not lead to major disputes. Being rational, business-minded adults, landowners and construction contractors are usually able to resolve disputes amongst themselves. After all, both stand to gain if the project is completed, and the contractor is paid.

Even if the parties can't easily resolve their disputes, and someone else needs to intervene, that somebody doesn't always need to be a judge or jury. Many construction disagreements call for mediation, during which a neutral third party helps the parties to the dispute negotiate a settlement. They might also go through arbitration, during which a third party renders a binding decision.

Litigation of construction disputes in Marysville, Ohio can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) occasions where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Marysville, Ohio

Delays: Some minor delays in a construction project are all but guaranteed to occur. Usually, if contracts require a specific completion date, the contractor will give itself longer than the project would take under ideal circumstances, to account for possible delays. Furthermore, construction contracts usually attempt to insure against delays, such as imposing fees on contractors if the project is delayed beyond a certain point. If no such clause is included in a contract, a court will usually award the client damages that could have been reasonably anticipated at the time the contract was entered into.

Refusal to Pay: Contractors can be on the other side of legal disagreements, as well. Sometimes, the landowners who hired them refuse to pay. This is usually because the landowner believes that the contractor didn't perform under the terms of the contract, or that the work was unsatisfactory. If this is the case, it may ultimately be up to a court to decide who is right. If the contractor did, in fact, do poor work, the landowner will be excused, at least in part, from his duty to pay. If, on the other hand, the work was satisfactory, the court will order the landowner to pay the contract price immediately, and may award further damages if the refusal to pay was done in bad faith, or if it caused foreseeable economic harm to the contractor.

Subcontractors: With big construction projects, contractors usually hire other, smaller contractors to do some of the work for them. This is usually work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. Nonetheless, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Lien: If the contractor wins in a case against the land owner, and the court orders the owner to pay the contractor for services rendered, the contractor needs a way to secure payment, if the owner refuses. In some cases, a mechanic's lien allows the contractor to force the sale of the land, and any improvements to it, in order to secure payment for the services it provided.

Can a Marysville, Ohio Attorney Help?

Construction disputes and disagreements can be very difficult to deal with alone. The assistance of a Marysville, Ohio real estate attorney can make the process of dealing with these disputes much quicker and easier.