Construction Dispute Law in California

When a property owner and a general contractor contract for a construction project to take place on some property in National City, California, whether it's a house, some landscaping, or a remodeling project, there is always a gamble that something can go wrong. In fact, at least a very minor setback may be more likely than not.

Most often, the owners of land and contractors can end disagreements before they get too serious, thus eliminating the need for litigation. Most contracts governing construction projects have built-in remedies for the most common problems, typically requiring the party that causes a delay or other problem to pay the other party a set fee.

Even if the parties can't easily resolve their disputes, and someone else needs to intervene, that somebody doesn't always need to be a judge or jury. Many construction disagreements call for mediation, during which a neutral third party helps the parties to the dispute negotiate a settlement. They might also go through arbitration, during which a third party renders a binding decision.

Because of the large cost in time and money involved, litigation in National City, California is regarded a last resort. However, in rare cases, it does become necessary.

Examples of Construction Disputes That Might Lead to Litigation in National City, California

Delays: Some minor delays in a construction project are all but guaranteed to occur. Typically, if contracts require a specific completion date, the contractor will give itself longer than the project would take under ideal circumstances, to account for possible delays. Moreover, construction contracts usually attempt to insure against delays, such as imposing fees on contractors if the project is delayed beyond a certain point. If no such clause is included in a contract, a court will usually award the client damages that could have been reasonably anticipated at the time the contract was entered into.

Refusal to Pay: Contractors can be on the other side of legal disagreements, as well. Sometimes, the landowners who hired them refuse to pay. This is typically because the landowner believes that the contractor didn't perform under the terms of the contract, or that the work was unsatisfactory. If this is the case, it may ultimately be up to a court to decide who is right. If the contractor did, in fact, do poor work, the landowner will be excused, at least in part, from his duty to pay. If, on the other hand, the work was satisfactory, the court will order the landowner to pay the contract price immediately, and may award further damages if the refusal to pay was done in bad faith, or if it caused foreseeable economic harm to the contractor.

Subcontractor Disputes: With very considerable construction projects, general contractors don't always have the resources to do all the work themselves, so they hire other contractors to do some of the work for them. Nonetheless, it is the general contractor who is ultimately responsible to the owner for the satisfactory completion of the project. So, it is very critical to the general contractor that subcontractors do a good job. If the subcontractor causes a delay or other issue, and the owner sues the general contractor as a result, the general contractor can then go after the subcontractor to recover whatever it lost in the lawsuit.

Mechanic's Liens: A mechanic's lien is a way for a contractor to secure payment if a landowner declines to pay. In such cases, if the contractor sues and wins, he or she can sometimes impose a mechanic's lien on the property he or she just worked on. This permits the contractor to force a sale of the property to cover the judgment. It is usually used when other attempts to secure payment fail.

Can a National City, California Attorney Help?

Disputes over construction delays or defects can be extremely taxing. Therefore, getting an efficient National City, California real estate attorney might mean the difference between success or failure in your business ventures.