Construction Dispute Law in Wisconsin

Construction contractors and landowners in Verona, Wisconsin sometimes end up in disagreements when a project that the landowner contracted for doesn't go exactly to plan. Truth be told, in any significant construction project, a few minor disputes are almost guaranteed.

Most often, landowners and construction contractors are able to resolve minor to moderate disagreements between themselves, and litigation is rarely necessary. Nobody likes litigation, so, to this end, most construction contracts have built-in remedies in case something goes wrong, like set price reductions if construction is delayed.

Even if a third party gets incorporated, it does not always need to be a court. Private mediators can assist the parties reach a settlement, or a private arbitrator who is an expert on construction litigation can render a binding decision, if mediation and negotiation fail and the parties can't resolve their dispute.

Litigation of construction disputes in Verona, Wisconsin can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) times where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Verona, Wisconsin

Delays in Construction: Delays are commonly points of contention between contractors and landowners. Contracts sometimes have clauses which explicitly state that the project needs to be completed by a certain date, or penalties will be imposed on the contractor (reduced payments, for example). However, if the contract doesn't contain such built-in remedies, or one party refuses to abide by them, litigation may be necessary. If a contractor causes a delay that it could have prevented, it will normally be liable to the landowner for any harm resulting from it.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will normally argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be accountable for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractor Disputes: When a construction company is contracted to complete a large project, there is normally a great deal of specialized work to be done which they aren't equipped to handle. As a result, they hire other contractors, who, in this arrangement, are subcontractors, to do some of the work. Nonetheless, the general contractor (the one that the landowner hired to do the work) is still accountable for the completion of the project - if a subcontractor causes a problem, the general contractor is on the hook for it. This sometimes leads to landowners suing general contractors for the mistakes of subcontractors. If the general contractor loses, and has to pay the client, the general contractor can then sue the subcontractor for whatever amount of money it had to pay.

Mechanic's Lien: If the contractor wins in a case against the land owner, and the court orders the owner to pay the contractor for services rendered, the contractor needs a way to secure payment, if the owner refuses. In some cases, a mechanic's lien authorizes the contractor to force the sale of the land, and any improvements to it, in order to secure payment for the services it provided.

Can a Verona, Wisconsin Attorney Help?

If you are involved in a dispute over a construction project, you should try to avoid litigation, and settle the matter as amicably as possible. However, litigation is sometimes imperative, and a Verona, Wisconsin construction disputes attorney can be of great help.