Construction Dispute Law in Washington

Construction contractors and landowners in Brier, Washington sometimes end up in disputes when a project that the landowner contracted for doesn't go exactly to plan. Truth be told, in any significant construction project, a few minor disputes are almost guaranteed.

Typically, contractors and landowners can resolve minor disputes amongst themselves, without having to resort to litigation. Frequently, construction contracts contain built-in remedies for mistakes and delays that can be easily corrected, such as payments to the owner for every day the project is delayed.

Even if someone else needs to get engaged to resolve a dispute, this does not automatically mean litigation is necessary. For example, the parties might attempt mediation, in which a neutral third party tries to help guide the parties to an agreement, but cannot render a binding decision himself. They might also agree to arbitration, during which a third party is able to render a binding decision. Arbitration is typically done through a private company, and may cost less than litigation, and is overseen by an arbitrator who is an expert in the relevant field.

Construction Dispute litigation in Brier, Washington is typically time-consuming and expensive. But it is sometimes necessary, typically as a last resort.

Examples of Construction Disputes That Might Lead to Litigation in Brier, Washington

Delays in Construction: Delays are frequently points of contention between contractors and landowners. Contracts sometimes have clauses which explicitly state that the project needs to be completed by a certain date, or penalties will be imposed on the contractor (reduced payments, for example). However, if the contract doesn't contain such built-in remedies, or one party refuses to abide by them, litigation may be necessary. If a contractor causes a delay that it could have prevented, it will typically be liable to the landowner for any harm resulting from it.

Owner's refusal to pay: Contractors can also be the victims in construction disputes. Sometimes, the person who hired them will refuse to pay the agreed-upon fee, or withhold a portion of it. This, without more, certainly constitutes breach of contract. However, in such cases, the owner will rarely go to court and say "I just didn't feel like paying, so I didn't." Alternatively, they will claim that they had a very good reason to withhold all or part of the payment, such as unsatisfactory work by the contractor. In these cases, the court has to determine if the owner has a valid reason for not paying. If it concludes that he or she does not, it will order the owner to pay the agreed-upon price.

Subcontractor Disputes: With very considerable construction projects, general contractors don't always have the resources to do all the work themselves, so they hire other contractors to do some of the work for them. However, it is the general contractor who is ultimately responsible to the owner for the satisfactory completion of the project. So, it is very crucial to the general contractor that subcontractors do a good job. If the subcontractor causes a delay or other problem, and the owner sues the general contractor as a result, the general contractor can then go after the subcontractor to recover whatever it lost in the lawsuit.

Mechanic's Liens: If the contractor sues a land owner and wins, he will likely obtain a monetary judgment. If the owner refuses to pay, the contractor needs some way to recover. This is where the mechanic's lien comes into play. It permits a contractor to force the sale of the land or other real property that he just worked on, and use those proceeds to cover costs.

Can a Brier, Washington Attorney Help?

Disputes over construction delays or defects can be extremely taxing. Therefore, getting an efficient Brier, Washington real estate attorney might mean the difference between success or failure in your business ventures.