Construction Dispute Law in Ohio

Owners of real estate in Mahoning County, Ohio often contract with other parties ("contractors") for construction on the property they own. Such projects are likely to suffer at least a few minor setbacks, and any project also carries the risk of major setbacks, delays, or unexpected costs.

In the overwhelming majority of instances, however, these problems are resolvable, and do not lead to major disputes. Being rational, business-minded adults, landowners and construction contractors are usually able to resolve disputes amongst themselves. After all, both stand to gain if the project is completed, and the contractor is paid.

Even if the parties can't easily resolve their disputes, and someone else needs to intervene, that somebody doesn't always need to be a judge or jury. Many construction disputes call for mediation, during which a neutral third party helps the parties to the dispute negotiate a settlement. They might also go through arbitration, during which a third party renders a binding decision.

Litigation of construction disputes in Mahoning County, Ohio can be extremely time-consuming, stressful, and costly. Nevertheless, there are (relatively rare) occasions where it is the only option.

Examples of Construction Disputes That Might Lead to Litigation in Mahoning County, Ohio

Delays: Some minor delays in a construction project are all but guaranteed to occur. Usually, if contracts require a specific completion date, the contractor will give itself longer than the project would take under ideal circumstances, to account for possible delays. Furthermore, construction contracts usually attempt to insure against delays, such as imposing fees on contractors if the project is delayed beyond a certain point. If no such clause is included in a contract, a court will usually award the client damages that could have been reasonably anticipated at the time the contract was entered into.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will usually argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be liable for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractors: With big construction projects, contractors usually hire other, smaller contractors to do some of the work for them. This is usually work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. However, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Lien: If the contractor wins in a lawsuit against the land owner, and the court orders the owner to pay the contractor for services rendered, the contractor needs a way to secure payment, if the owner refuses. In some cases, a mechanic's lien allows the contractor to force the sale of the land, and any improvements to it, in order to secure payment for the services it provided.

Can a Mahoning County, Ohio Attorney Help?

Disputes over construction delays or defects can be extremely taxing. Therefore, getting an experienced Mahoning County, Ohio real estate attorney might mean the difference between success or failure in your business ventures.