Construction Dispute Law in Michigan

When the owner of some real estate and a contractor enter an agreement for a construction project in Clintonship, Michigan, be it a house, landscaping project, or large office building, there's always a chance that issues will come up, no matter how careful everyone is. A few minor setbacks are almost inevitable, in fact.

In the majority of cases, it's possible for landowners and contractors to resolve disagreements amicably. There are many ways to do this, such as a simple verbal agreement to lower the contract price due to a mistake made by the contractor, for example, or an agreement to a slight price increase in the event of unforeseen obstacles beyond the control of either party.

Even if someone else needs to get engaged to resolve a dispute, this does not automatically mean litigation is necessary. For example, the parties might attempt mediation, in which a neutral third party tries to help guide the parties to an agreement, but cannot render a binding decision himself. They might also agree to arbitration, during which a third party is able to render a binding decision. Arbitration is typically done through a private company, and may cost less than litigation, and is overseen by an arbitrator who is an expert in the relevant field.

Litigation of a Clintonship, Michigan construction dispute is never something that anyone wants to do. Nonetheless, there are sometimes no other avenues.

Examples of Construction Disputes That Might Lead to Litigation in Clintonship, Michigan

Delays: If the contractor is culpable in a major delay in a construction project (a delay of weeks or months, for example), a lawsuit could result. If the contract particularly states that completion by a specific date is very important, or the builder has a good reason to know this, a court will often award the owner compensation for any economic harm caused by a delay.

Refusal to Pay: Contractors can be on the other side of legal disagreements, as well. Sometimes, the landowners who hired them refuse to pay. This is typically because the landowner believes that the contractor didn't perform under the terms of the contract, or that the work was unsatisfactory. If this is the case, it may ultimately be up to a court to decide who is right. If the contractor did, in fact, do poor work, the landowner will be excused, at least in part, from his duty to pay. If, on the other hand, the work was satisfactory, the court will order the landowner to pay the contract price immediately, and may award further damages if the refusal to pay was done in bad faith, or if it caused foreseeable economic harm to the contractor.

Subcontractors: With big construction projects, contractors typically hire other, smaller contractors to do some of the work for them. This is typically work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. Nonetheless, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Lien: If the contractor wins in a case against the land owner, and the court orders the owner to pay the contractor for services rendered, the contractor needs a way to secure payment, if the owner refuses. In some cases, a mechanic's lien permits the contractor to force the sale of the land, and any improvements to it, in order to secure payment for the services it provided.

Can a Clintonship, Michigan Attorney Help?

If you are involved in a dispute over a construction project, you should try to avoid litigation, and settle the matter as amicably as possible. However, litigation is sometimes crucial, and a Clintonship, Michigan construction disputes attorney can be of great help.