Construction Dispute Law in Alabama

When a property owner and a general contractor contract for a construction project to take place on some property in Scottsboro, Alabama, whether it's a house, some landscaping, or a remodeling project, there is always a chance that something can go wrong. In fact, at least a very minor setback may be more likely than not.

Most often, landowners and construction contractors are able to resolve minor to moderate disagreements between themselves, and litigation is rarely necessary. Nobody likes litigation, so, to this end, most construction contracts have built-in remedies in case something goes wrong, like set price reductions if construction is delayed.

And even if disputes can't be resolved so easily, the courts still don't necessarily have to get involved. For example, a construction contract may require mediation before any further action is taken. Mediation is a process by which a third party tries to guide the parties to the dispute to a settlement. The mediator cannot, however, render any binding decision. Another avenue is arbitration. This is where the parties go to a private arbitration service, which can render a binding judgment (generally enforceable through contract law, as the parties agree in advance to abide by the arbitrator's decision). Arbitration has benefits over litigation, as the parties can have a say in choosing the arbitrator (allowing them to have their case arbitrated by an expert on construction disputes, for example).

Because of the large cost in time and money involved, litigation in Scottsboro, Alabama is regarded a last resort. However, in rare cases, it does become necessary.

Examples of Construction Disputes That Might Lead to Litigation in Scottsboro, Alabama

Delays: Some minor delays in a construction project are all but guaranteed to occur. Usually, if contracts require a specific completion date, the contractor will give itself longer than the project would take under ideal circumstances, to account for possible delays. Furthermore, construction contracts usually attempt to insure against delays, such as imposing fees on contractors if the project is delayed beyond a certain point. If no such clause is included in a contract, a court will usually award the client damages that could have been reasonably anticipated at the time the contract was entered into.

Owner's refusal to pay: if the contractor finishes a project to specifications, and the owner of the property doesn't pay the contractor, the contractor will most likely file a lawsuit to recover the agreed-upon price. In such cases, the owner will usually argue that the contractor's work wasn't of acceptable quality. In these cases, the court must decide who first breached the contract. In these cases, it's the party who did not breach first who wins the lawsuit. If the court finds that the contractor breached the contract through sub-quality work product, the owner will not be liable for payment (though he may have to pay for materials and labor), and if the court finds that the construction was acceptable, the owner has to pay, because he is the party in breach.

Subcontractors: With big construction projects, contractors usually hire other, smaller contractors to do some of the work for them. This is usually work of a specialized nature, which the general contractor isn't equipped to handle (such as plumbing or electrical wiring). The general contractor is the one who is responsible for the satisfactory completion of the project. If a subcontractor makes a mistake, or causes a delay, the general contractor is ultimately liable to the person who hired them. Nonetheless, if they are sued for the mistakes of a subcontractor, and lose, they can then sue the subcontractor to recover their losses.

Mechanic's Liens: Sometimes, when a contractor wins in a case against the landowner who hired him or her, and obtains a court order for payment, the contractor will still refuse to pay. Since a money judgment isn't worth much without a way to enforce it, the laws of many states have evolved to allow what's known as a "mechanic's lien." As a last resort, if a landowner refuses to pay the contractor for work done on the property, the contractor can force a sale of the property, and keep the proceeds, up to the amount of money owed.

Can a Scottsboro, Alabama Attorney Help?

If you have a construction dispute, you should first try to resolve it amicably with the other party. If this fails, it is almost always crucial to hire a Scottsboro, Alabama construction disputes attorney, who can advise you on the next steps in the process.